🚀 New Feature Alert : Introducing RDash Activity Schedule! Plan, Track and Collaborate.  Check Now
Home / Blog / Unit Price Contracts in Construction

Unit Price Contracts in Construction

Unit Price Contracts in Construction

Share this article :

How unit price contracts work

In construction, a unit price contract is an agreement where the payment is determined by the number of specific tasks or units completed. Each unit, such as a meter of piping or a square meter of flooring, has a set price, and the total cost depends on how many units are actually done. 

For example, if a contractor is building a road, the contract may say they will be paid ₹1,000 per meter of road laid. If they lay 100 meters, they earn ₹1,00,000.

The owner pays only for the work that is actually done. This makes it fair for both the owner and the contractor when the exact amount of work is hard to know in advance.

When should you use a unit price contract?

A unit price contract is best when:

  • The total quantity of work is uncertain at the start.
  • The project involves repeated tasks, like laying pipes or pouring concrete.
  • It is hard to estimate the full scope, but unit costs are known.

This kind of contract allows greater adaptability during the project. If the scope increases or decreases, the cost changes based on the actual work done.

Unit pricing in other contract types

1. Time and Materials with Unit Pricing

In this case, the contractor is paid for labor hours and materials used, but unit rates are added for tasks like excavation or painting. It gives more control over specific parts of the work.

2. Cost-Plus Contract with Unit Prices

Here, the contractor is paid for the actual cost of the work plus a fee or percentage for profit. Unit prices are sometimes used for parts of the job to set limits on how much can be charged.

3. Lump Sum Contract with Unit Price for Extras

With a lump sum contract, the overall cost is predetermined and does not change. But if the client asks for extra work, those tasks might be priced using unit rates agreed in advance. This keeps changes transparent and fair.

Advantages of unit price contracts

Unit price contracts offer several benefits, especially for construction projects where the full scope of work is unclear at the beginning. Here are some key advantages:

Flexibility in Scope

Unit price contracts are ideal when the total amount of work isn’t known in advance. For example, if you’re laying underground cables, you might not know how many meters are needed until digging begins. With unit pricing, you pay for the actual amount completed.

Easier Cost Tracking

Because each task or material is priced per unit, it’s easier to track how much money is being spent. If 100 units are used, and each costs ₹500, then you know the total is ₹50,000. This makes budgeting and monitoring simple for both the client and the contractor.

Fair Payment for Both Sides

Contractors are paid for the exact quantity of work done. This means they don’t lose money if more work is needed, and clients don’t overpay if the work is less than expected. It’s a win-win.

Useful for Repetitive Work

Unit price contracts work very well when the same kind of work is repeated many times, such as laying tiles, installing pipes, or pouring concrete slabs. Each action can be priced and measured easily.

Disadvantages of unit price contracts

While unit pricing is helpful in many situations, it also has a few downsides:

Harder to Estimate Final Cost

Since the total quantity of work isn’t fixed, it’s difficult to know exactly how much the project will cost in the end. This can make planning budgets more challenging.

More Supervision Needed

To make sure the correct number of units are reported, someone must keep a close watch on the work being done. If there is no proper tracking, the contractor might claim more units than were actually completed.

Slower Billing Process

Each item or activity must be measured and recorded before billing. This takes more time compared to a lump sum contract, where the payment is made in large fixed stages.

Potential for Disputes

If there is any confusion about how units are measured or what counts as one unit, disagreements may arise between the contractor and the client.

Challenges of unit price contract

Even though unit pricing is simple in theory, putting it into practice can have its own difficulties:

Unit Price Contracts

1. Accurate Measurement

For a unit price contract to work well, every unit of work must be measured correctly. If mistakes happen, it can lead to overpayments or underpayments.

2. Detailed Scope Description

Each unit must be clearly defined in the contract. For example, what exactly counts as “one unit” of excavation? Without proper clarity, both parties can have different understandings, leading to confusion later.

3. Changes in Material Rates

If the cost of materials increases suddenly, the unit price agreed in the contract may no longer be fair to the contractor. At the same time, if prices drop, the client might feel they are overpaying.

4. Site Conditions

Sometimes, unexpected conditions at the worksite (like hard rock during excavation) can make the work more difficult than planned. But with a fixed unit price, the contractor still gets paid the same amount per unit, which may not cover the extra effort.

Example of unit price contract

Let’s say a city hires a contractor to build a new water pipeline. The total length of the pipeline is not fully known at the start because the land survey is still ongoing. Instead of signing a fixed-price contract, they agree to a unit price contract.

The contract might include the following:

Work ItemUnitUnit Price (in ₹)
Digging trenchPer meter₹400
Laying 6-inch PVC pipePer meter₹600
Backfilling and compacting soilPer meter₹300

If the contractor ends up laying 1,000 meters of pipe, they will be paid:

  • ₹400 × 1,000 = ₹4,00,000 for trenching
  • ₹600 × 1,000 = ₹6,00,000 for pipe laying
  • ₹300 × 1,000 = ₹3,00,000 for backfilling

Total = ₹13,00,000

This method ensures that the contractor is paid for the actual work done and not a fixed estimate. If the pipeline is longer or shorter than expected, the final price changes based on real measurements.

Mitigating risk with unit pricing

Unit price contracts help reduce risk for both the contractor and the client, especially in uncertain or changing conditions.

1. For the Client

  • No overpayment: The client only pays for what is actually done.
  • Budget control: Since each unit has a clear cost, the client can stop or reduce work if needed to manage their budget.

2. For the Contractor

  • Fair payment: The contractor is paid for each unit completed. If more work is needed, they earn more fairly.
  • Scope flexibility: If site conditions change (like needing to dig deeper), the contract still works by charging per unit.

3. Reducing Disputes

By agreeing on unit prices early, both parties avoid confusion during the project. This reduces arguments about cost increases or changes in quantity.

4. Clear Records

Each completed unit must be measured and approved. This creates a clear and shared record of work done, which protects both sides legally.

What costs go into pricing a unit?

When contractors decide the unit price for any work item, they include several types of costs. These help them ensure they don’t lose money and cover all the effort and materials involved.

Unit Price Contracts

Here are the key components:

1. Material Cost

The price of items needed to do the job. For example, in pipe laying, this includes the cost of the pipe, joints, and glue.

2. Labor Cost

Wages paid to workers who carry out the job. This includes machine operators, helpers, and skilled laborers.

3. Equipment Cost

Some tasks require machines (like excavators or compactors). Their rental charges, fuel, and maintenance are part of the unit price.

4. Overhead

This includes office costs, project management, safety gear, travel, and other support services. Even if not directly used on-site, these costs support the project and are added to each unit.

5. Profit Margin

After adding all expenses, contractors include a profit percentage. This ensures the business earns a reasonable return for taking on the work.

6. Risk Factor

Sometimes, a small extra charge is added to cover uncertainties, like changes in soil condition or delays due to weather. This helps protect the contractor from losses.

Related Tags : Unit Price Contracts
Table of Contents
Ready to Supercharge⚡
your Projects?
Experience the revolution in the construction industry with streamlined, seamless and efficient project management.

RDash Videos

Ready to get started?

Fill out the form below and we will contact you as soon as possible.

Solutions
Who We Serve
Services
Pricing
Company
Resources
Play Video
Play Video